top of page

BJWSA: Paris Island

Project Details

Client: Beaufort Water & Sewer Authority

Location: Beaufort ,South Carolina

Scope: Construction Inspection

ASCS provided an inspector for construction observation services for the demolition and rehabilitation of pump stations, and improvements to the collection system as part of the ISM Group 1 - Phase 1 and 2 pump station upgrade projects. The project entails the demolition of 4 pump stations, rehabilitation of 3 pump stations, and improvements to approximately 3500 feet of 8", 12" and 18" gravity sewer systems. The inspector's responsibilities are to observe construction progress, maintain daily construction progress reports, and submitted reports to engineer for review.

bottom of page