top of page

Starks Industrial Park Water Main Improvements

Project Details

Client: Charleston Water System

Location: Charleston, South Carolina

Scope: Design

This project includes the identification of new locations for approximately 9150 linear feet of 8" pipe, fire hydrants and appurtenances; and the elevation of fire protection for the area based on location of fire hydrants, system pressures, and fire demands. Existing information pertaining to the current water usage of the existing customers in the area will be gathered along with any plans for future commercial development. The tasks to be performed includes: producing the Basis of Design Report, providing preliminary investigations and surveys, procuring required permits, producing plans and specifications, providing construction cost estimates, producing bid documents, soliciting bids from approved contractors, providing asbuilt drawings and completing all project close-out documentations.